PROJECTS / Centrale Thermique de Lomé 100 MW Power Station

Centrale Thermique de Lomé 100 MW Power Station

Sub-Saharan Africa

October 22, 2020

K&M served as Transaction Advisor to the and the state utility, Compagnie d’Energie Electrique du Togo (CEET). K&M provided technical advice and negotiation support for the rehabilitation, repowering and expansion of the 100 MW Centrale Thermique de Lomé power plant. K&M conducted a technical, commercial and financial review of the project and assisted in the selection of a private developer. K&M reviewed existing legislation and the regulatory framework, analyzed privatization options, and structured the project on a BOT basis. K&M developed the bid document package, evaluated the developer’s proposal, and provided support to the Ministry in the negotiation of all the agreements with the developer.